Design of pouring system for aluminum alloy camshaft cover die-casting mold
Time:2024-05-30 08:44:32 / Popularity: / Source:
As installation carrier of camshaft, camshaft cover is tightly connected with cylinder head and used to seal cylinder head, valve chamber and camshaft. It is a key component of engine assembly. Compared with other automotive parts, camshaft covers are prone to deformation, require high surface quality and dimensional accuracy. Die castings are widely used in many industrial fields, especially in automobile manufacturing. If casting system of die-casting mold is unreasonably designed, air is easily trapped during high-speed die-casting process, defects such as pores, shrinkage cavities, and shrinkage porosity will be formed after solidification, which will adversely affect mechanical properties of die-casting parts, especially large and medium-sized precision and complex parts.
Computer simulation has been widely used in the field of die casting. Through simulation of mold filling, solidification and other processes, casting defects can be effectively predicted and mold design optimized. In order to optimize process design, improve die casting quality and shorten production cycle. Based on ProCAST software, die-casting mold pouring system of an automobile aluminum alloy camshaft cover part is optimized and designed to provide a reference for its application.
Computer simulation has been widely used in the field of die casting. Through simulation of mold filling, solidification and other processes, casting defects can be effectively predicted and mold design optimized. In order to optimize process design, improve die casting quality and shorten production cycle. Based on ProCAST software, die-casting mold pouring system of an automobile aluminum alloy camshaft cover part is optimized and designed to provide a reference for its application.
Graphical results
Aluminum alloy camshaft cover part is a rectangular frame structure, and its three-dimensional model is shown in Figure 1. Outline size is 361mm*160mm*44mm, volume is about 4.34*105mm3, maximum wall thickness is 8mm (see circled position in Figure 1a), and minimum wall thickness is 4mm. Based on structural characteristics of casting and design theory of gating system, three gating system schemes were designed, as shown in Figure 2. Option 1 has 6 ingates, distributed at 5 beam positions and ends with U-shaped grooves on long side of casting. In order to prevent air entrainment and shrinkage cavities at semicircular platform near gate on the short side of casting, an overflow groove is added in Plan 2, as shown in Figure 2b. Considering that the two horizontal sprues at the end of casting are prone to air entrainment at intersection of liquid flows, Plan 3 merges the two inner gates on the left into one, retains overflow groove added in Plan 2, as shown in Figure 2c .
(a) Outside of casting
(b) Inside of casting
Figure 1 Three-dimensional view of camshaft cover casting
Figure 1 Three-dimensional view of camshaft cover casting
Metal density p/(g*cm-3) | Charging speed v/(m*s-1) | Filling time t/s | Internal gate cross-sectional area Ag/mm2 | Inner gate thickness d/mm | Casting quality m/g |
2.4 | 50 | 0.03 | 346 | 2.4 | 1305 |
Table 1 Main design parameters of die-casting mold
(a) Option 1
(b) Option 2
(c) Option 3
Figure 2 Design scheme of camshaft cover casting gating system
Casting material | Liquidus temperature/℃ | Solidus temperature/℃ | Pouring temperature/℃ | Casting mold heat transfer coefficient/(W*m-2*K-1) | Casting mold heat transfer coefficient/(W*m-2*K-1) |
A380 | 598 | 510 | 670 | 1500 | 1000 |
Mold material | Mold preheating temperature/℃ | Punch diameter/mm | Slow injection speed/(m*s-1) | Fast injection speed/(m*s-1) | Ambient temperature/℃ |
H13 | 210 | 100 | 0.2 | 3 | 20 |
Table 2 Calculation conditions
Simulation results of filling process of three gating system design schemes are shown in Figure 3. Figure 3a shows filling process of Scheme 1. It can be seen that molten metal enters mold cavity along sprue, which satisfies sequential filling as a whole. However, due to frame structure of camshaft cover, molten metal diverts and merges multiple times, increasing tendency of gas entrainment. When mold filling rate is 50%, molten metal merges at circle marked position, compressed gas cannot be discharged through cavity formed by casting beam, easily causing gas entrainment and welding marks here. Filling process of Scheme 2 is shown in Figure 3b. Compared with Scheme 1, flow pattern of molten metal is similar. When filling rate is 50%, molten metal also forms a flow convergence at circle marked position, but merged flow is in cavity channel, possibility of producing pores and weld marks is relatively low. At the same time, since Plan 2 has an overflow groove on one side of casting truncated cone, air entrainment and shrinkage cavity defects can be reduced. Compared with the first two options, Scheme 3 has a confluence position of liquid flow in circle-marked area close to the side of overflow tank and also at position of cavity channel, see Figure 3c. Option 3 avoids intersection and mutual impact of the two molten metals inside casting, thereby reducing possibility of eddy currents, air entrapment, and oxidized slag inclusions, pouring and filling process is more reasonable. Judging from filling status when mold filling rate is 70% and 95%, filling conditions of the three gating system design schemes are similar. After mold cavity is filled, cold and dirty metal liquid, excess metal liquid and air in cavity can smoothly enter overflow tank and be discharged.
Simulation results of filling process of three gating system design schemes are shown in Figure 3. Figure 3a shows filling process of Scheme 1. It can be seen that molten metal enters mold cavity along sprue, which satisfies sequential filling as a whole. However, due to frame structure of camshaft cover, molten metal diverts and merges multiple times, increasing tendency of gas entrainment. When mold filling rate is 50%, molten metal merges at circle marked position, compressed gas cannot be discharged through cavity formed by casting beam, easily causing gas entrainment and welding marks here. Filling process of Scheme 2 is shown in Figure 3b. Compared with Scheme 1, flow pattern of molten metal is similar. When filling rate is 50%, molten metal also forms a flow convergence at circle marked position, but merged flow is in cavity channel, possibility of producing pores and weld marks is relatively low. At the same time, since Plan 2 has an overflow groove on one side of casting truncated cone, air entrainment and shrinkage cavity defects can be reduced. Compared with the first two options, Scheme 3 has a confluence position of liquid flow in circle-marked area close to the side of overflow tank and also at position of cavity channel, see Figure 3c. Option 3 avoids intersection and mutual impact of the two molten metals inside casting, thereby reducing possibility of eddy currents, air entrapment, and oxidized slag inclusions, pouring and filling process is more reasonable. Judging from filling status when mold filling rate is 70% and 95%, filling conditions of the three gating system design schemes are similar. After mold cavity is filled, cold and dirty metal liquid, excess metal liquid and air in cavity can smoothly enter overflow tank and be discharged.
(a) Scheme 1 filling process
(b) Scheme 2 filling process
(c) Scheme 3 filling process
Figure 3 Filling process of castings under three pouring schemes
Figure 3 Filling process of castings under three pouring schemes
(a) Option 1
(b) Option 2
(c) Option 3
Figure 4 Solidification process of three pouring system solutions
Figure 4 Solidification process of three pouring system solutions
(a) Option 1
(b) Option 2
(c) Option 3
Figure 5 Prediction of shrinkage cavities in castings under different pouring schemes
Figure 5 Prediction of shrinkage cavities in castings under different pouring schemes
(a) Filling process
(b) Solidification process
Figure 6 Filling process and solidification process of improved plan
Through analysis and comparison of filling and solidification process, shrinkage cavities and shrinkage porosity, it is believed that option 3 has the best effect. However, according to filling simulation results when mold is 50% filled in Figure 3c, molten metal convergence is on cavity channel, and filling and exhaust conditions are good. At the same time, shrinkage cavity and shrinkage porosity simulation results show that pores at casting B have not changed significantly in the three schemes. Therefore, it is considered to remove overflow groove near B in Figure 4f, which can reduce temperature in this area, accelerate solidification, and improve die-casting efficiency. Simulation results of shrinkage cavities, porosity and trial castings of improved scheme are shown in Figure 7. Compared with results in Scheme 3 (see Figure 5c), Figure 7a shows that one of the three shrinkage cavities in thick area of casting is directly eliminated, and volume of the other two shrinkage cavities is reduced. Volume of shrinkage cavities in casting is 1.43*10- 3cm3. Simulation results show that optimized scheme meets casting quality requirements, so optimized scheme is used for mold opening and mold trial. Trial mold casting is processed and shown in Figure 7b.
Figure 6 Filling process and solidification process of improved plan
Through analysis and comparison of filling and solidification process, shrinkage cavities and shrinkage porosity, it is believed that option 3 has the best effect. However, according to filling simulation results when mold is 50% filled in Figure 3c, molten metal convergence is on cavity channel, and filling and exhaust conditions are good. At the same time, shrinkage cavity and shrinkage porosity simulation results show that pores at casting B have not changed significantly in the three schemes. Therefore, it is considered to remove overflow groove near B in Figure 4f, which can reduce temperature in this area, accelerate solidification, and improve die-casting efficiency. Simulation results of shrinkage cavities, porosity and trial castings of improved scheme are shown in Figure 7. Compared with results in Scheme 3 (see Figure 5c), Figure 7a shows that one of the three shrinkage cavities in thick area of casting is directly eliminated, and volume of the other two shrinkage cavities is reduced. Volume of shrinkage cavities in casting is 1.43*10- 3cm3. Simulation results show that optimized scheme meets casting quality requirements, so optimized scheme is used for mold opening and mold trial. Trial mold casting is processed and shown in Figure 7b.
(a) Improvement plan shrinkage and porosity
Simulation results
Simulation results
(b) Trial die casting
Figure 7 Shrinkage simulation results and trial castings of improved scheme
Figure 7 Shrinkage simulation results and trial castings of improved scheme
(a) D of casting
(b) Casting E
(c) Casting F
(d) Casting cutting section
Figure 8 Casting defect detection X-ray flaw detection
Figure 8 Casting defect detection X-ray flaw detection
In conclusion
(1) Reducing number of lateral sprues in frame-type camshaft cover castings can improve flow pattern of molten metal and reduce internal pores caused by gas entrainment.
(2) Optimization plan of gating system reduces temperature in this area by removing overflow groove near semicircular cone of casting, can eliminate pores formed by solidification shrinkage of many thick parts. The overall solidification time of casting is shortened to 46.7 seconds, which improves production efficiency.
(3) Casting cutting and X-ray flaw detection only found two holes in non-critical locations, and quality of casting meets usage requirements.
(2) Optimization plan of gating system reduces temperature in this area by removing overflow groove near semicircular cone of casting, can eliminate pores formed by solidification shrinkage of many thick parts. The overall solidification time of casting is shortened to 46.7 seconds, which improves production efficiency.
(3) Casting cutting and X-ray flaw detection only found two holes in non-critical locations, and quality of casting meets usage requirements.
Recommended
Related
- Research status and development trends of high-strength and tough die-cast magnesium alloys11-23
- N93 mobile phone battery cover injection mold design key points11-23
- Mold design affects quality of aluminum die castings11-22
- Seven plastic surface treatment processes you must know11-22
- Quick design of technical parameters for local pressurization of die casting11-21